Life cycle oriented design of a GT + 1PSH HRSG type CCGT power plant .
(2009-12)
In the present work, a life cycle oriented approach is used for designing power plants in a way they can satisfy the desired demand along the whole time horizon, while selected economic indicators of the project are ...
Strategy for optimization of CCGT power plants by solving a simple nonlinear equations system and constraint equations.
(2010-07)
A strategy for the solution of the optimization problem of minimum cost of combined cycle gas turbine
power plants is presented. Specific relationships, valid at the optimal solution, among selected decision
variables ...
Aprendizaje interdisciplinar en red entre estudiantes de ingeniería de universidades argentinas.
(2021-07)
La implementación de una educación universitaria basada en competencias resalta la necesidad de implementar estrategias de enseñanza y aprendizaje innovadoras que promuevan la formación articulada e interdisciplinaria de ...
Experiencia piloto para la articulación vertical de la formación por competencias en Ingeniería Civil.
(2021-10)
Las carreras de ingeniería se encuentran actualmente en el proceso de adaptación a una educación basada en competencias en virtud de la propuesta de estándares desarrollada por el Consejo Federal de Decanos de Ingeniería ...
Development of optimization models for food processing operations with focus on adding value to by products.
(2018-09)
Development of optimization models for food processing operations with focus on adding value to by products.. (Resumen)
Implications of a state-space approach for the economic optimal design of a NGCC power plan.
(2014-10)
A detailed state-space approach is here embedded in the optimization model for the economic design of a new natural gas combined cycle (NGCC) power plant. This proposal comprehensively quantifies the impact of different ...
Economic implications when considering availability in the optimal design and operation of a NGCC power plant.
(2012-09)
- Traditionally, power plants are designed to fulfll a pre-specified external demand, usually by oversizing the existing equipment, which implies excessive capital costs and might even result in designs that cannot satisfy ...
Optimal management policies for the economic optimal dispatch of a hydrothermal power grid.
(2016-06)
Presentación en diapositivas realizada en : EngOpt 2016, 19 al 23 de Junio de 2016, Foz de
Iguazú, Brasil.