A strategy for the solution of the optimization problem of minimum cost of combined cycle gas turbine
power plants is presented. Specific relationships, valid at the optimal solution, among selected decision
variables are used to introduce new constraints to the optimization problem. Then, the feasible region
is reduced to a “single point”, and the resolution strategy becomes equivalent to solving the resultant
set of non-linear equations system and constraint equations so achieved to optimize the system. This
approach can also be used to achieve reduced models for real time optimization problems.
Description
Keywords
Plantas de energía, Ingeniería, Estrategias de optimización
Citation
International Conference on Continuous Optimization ICCOPT 2010, 26 al 29 de Julio de 2010, Santiago, Chile
Endorsement
Review
Supplemented By
Referenced By
Creative Commons license
Except where otherwised noted, this item's license is described as openAccess